Project Overview
Demolition of an existing 480V delta service and installation of a new 480V wye distribution system at the control tower and generator buildings — including a new 400A utility feed, emergency generator receptacle, and full grounding/lightning protection.
Scope of Work
- Demolish existing 480V delta service
- Install new 480V wye distribution
- Control tower + generator building work
- New 400A utility feed
- Emergency generator receptacle
- Grounding & lightning protection